How a job runs

Five steps, and the first one is not the roof

Most of the difference between a good solar install and an expensive one is decided before anyone puts up a ladder. This is the order we work in and roughly how long each part takes.

01

01

Meter data

We ask for a fortnight of half-hourly readings from your smart meter, or a manual log if you do not have one. That gives us a consumption curve rather than an annual total, and the curve is what an array should be sized against. It is free, it is not a commitment, and if it shows solar is a poor fit for your household we will say so at this point rather than at the quote.

Two weeks

typical

02

02

Survey

On the roof, not on an aerial photograph. Pitch and orientation measured, a horizon scan for shading through the year, the covering and the battens inspected, and the consumer unit and earthing checked. Where a roof needs work before an array goes on it, this is where that gets found.

Half a day

typical

03

03

Design and quote

An array sized to the overlap between what you generate and what you use, a string layout, an inverter specification, and a written quote with both payback figures on it: the one every quote prints, and the one after degradation, export tariffs, maintenance and one inverter. No pressure, no expiring discount.

Three to five days

typical

04

04

Install

Scaffold, mount, panels, DC and AC first fix, inverter, isolators, commissioning and a system test. Longer where slate has to come off by hand for an in-roof tray, and longer again if the weather closes in with the roof open.

Two to four days

typical

05

05

Handover

MCS certificate, electrical installation certificate, DNO notification, your export tariff application, and the operating and maintenance manual. Then, one year on, we send your quoted figures next to what the meter actually reported.

Two weeks after

typical

Brightfell installers fitting panels on a pitched roof

Paperwork

What you are handed at the end

Five documents. Ask any installer for this list before you sign anything; the ones who hesitate are telling you something.

MCS certificate

Registers the installation and is what an export tariff application needs.

Electrical installation certificate

The BS 7671 certificate for the electrical work, signed by the person who did it.

DNO notification

Confirmation your distribution operator has been told the array exists and at what capacity.

Operating and maintenance manual

Panel and inverter datasheets, warranty terms, isolator locations and the service interval.

Handover figures

The quoted generation and payback, in writing, so there is something to compare the meter against.

Next step

Step one costs nothing

Send us a fortnight of meter readings and a postcode. We will tell you whether the roof is worth surveying before either of us spends a morning on it.